Order 1,000 custom boxes and you may receive 1,060, or 970. That’s normal in corrugated manufacturing, not a counting mistake. Overs and unders come from how box runs are set up and inspected, and most suppliers spell out an allowed range, called the tolerance, in their quotes or terms.
Why can’t a box plant run the exact quantity?
A box run starts with a stack of corrugated sheets, or blanks, and every stage takes a few out:
| Stage | Where boxes are lost |
|---|---|
| Setup | The first sheets through a flexo folder-gluer or rotary die-cutter are used to set scores, slots, cuts and glue |
| Sheets are pulled until the print registration (colors lined up with each other and with the box panels) is right | |
| Running | Occasional misfeeds, jams or warped sheets |
| Inspection | Boxes with print, glue or cut defects are pulled |
| Die-cut layouts | When several boxes come from one sheet, quantities move in steps of that number |
| Bundling | Boxes are counted into bundles and stacked into full pallet loads |
The plant has to decide how many extra sheets to start with before it knows how many the run will consume. Start too few and the order ships short; start too many and it ships over. Setup waste is roughly fixed per run, so on a short run it’s a bigger share of the order.
How much over or under is normal?
There’s no single industry rule. Many packaging suppliers state a tolerance of about 10% either way. One corrugated box maker’s customer FAQ, for example, states a ±10% over-run or under-run, so an order of 1,000 boxes may ship and bill anywhere from 900 to 1,100. A packaging-buying guide gives the same typical margin and notes that overs, not unders, are the usual default. Printing trade associations once published similar “trade customs”; a regional printing association now describes its replacement guidelines as voluntary and negotiable.
So treat 10% as a reference point, not a promise. Your supplier’s quote or terms set the actual number.
| Term | Meaning | On a 1,000-box order at ±10% |
|---|---|---|
| Overrun (overs) | Shipped above the order | Up to 1,100 |
| Underrun (unders) | Shipped below the order | As few as 900 |
| Tolerance | The allowed range | 900 to 1,100 |
| No unders | Guaranteed minimum | At least 1,000, with some overs likely |
| No overs | Guaranteed maximum | At most 1,000, with some unders likely |
How are overs and unders billed?
Commonly, you’re billed for the quantity actually shipped, as long as it falls inside the agreed tolerance. Overs within tolerance are invoiced; unders reduce the invoice. Practices differ, so read the terms on your quote and compare the invoice to the packing list, not to the PO.
What if you need an exact quantity?
Say so before the order is quoted. Some uses really do need a firm count, such as kits that pair one box with one product or a contract that specifies an exact delivery. Your options:
- Ask for no unders. The plant starts with more extra sheets so it doesn’t fall short. You’ll likely receive overs, and the price may change.
- Ask for a tighter tolerance. Possible on some jobs, at a price that reflects the extra care and sheets.
- Let the plant hold the overs. In a stocking program, extra boxes simply go into your inventory for the next release instead of crowding your dock.
How do you plan around overs and unders?
- Order with a buffer. If you need 1,000 boxes to finish a job, don’t order exactly 1,000 without a no-unders agreement.
- Put the tolerance on the PO. Write the tolerance you agreed to on the purchase order so receiving knows what’s acceptable.
- Ask how a blanket order handles it. Under a blanket order, find out whether the tolerance applies to each production run or to each delivery taken from stock.
- Count by bundle at receiving. Bundles × boxes per bundle is faster than counting loose boxes, and the bundle count should be on the label.
- Ask about minimums at the same time. Short runs carry proportionally more setup waste; see minimum order quantities, explained.